Justia Zoning, Planning & Land Use Opinion Summaries
Articles Posted in Energy, Oil & Gas Law
Umatilla County v. Dept. of Energy
The case involves a dispute over the approval of a site certificate for the construction of a wind energy facility in Umatilla County, Oregon. The Energy Facility Siting Council granted the certificate to Nolin Hills Wind, LLC, despite the proposed facility not complying with a local siting criterion requiring a two-mile setback between any turbine and a rural residence. Umatilla County sought judicial review of the council's decision, arguing that the council should have required Nolin Hills to comply with the two-mile setback rule.The case was reviewed by the Supreme Court of the State of Oregon. The court noted that the council had the authority to approve the proposed energy facility despite its failure to comply with the two-mile setback rule. The court also noted that the council had the authority to approve the proposed facility even if it did not pass through more than three land use zones and even if it did not comply with all of the county’s recommended substantive criteria.The Supreme Court of the State of Oregon affirmed the council's decision, concluding that the council was authorized to issue a site certificate for the proposed wind facility notwithstanding the failure of the proposed facility to comply with the two-mile setback rule. The court found that the council was not required to reject a proposed facility simply because it did not comply with a local criterion. The court also rejected the county's argument that the council erred in concluding that the proposed facility "does otherwise comply with the applicable statewide planning goals." View "Umatilla County v. Dept. of Energy" on Justia Law
Mojalaki Holdings v. City of Franklin
The case involves Mojalaki Holdings, LLC and GSSG New Hampshire, LLC (the plaintiffs) who appealed a decision by the City of Franklin Planning Board (the Board) that denied their site plan application to install a solar panel array on a piece of land owned by Mojalaki. The proposed solar panel array required the installation of new utility poles and the removal of mature trees to ensure sufficient sunlight. The land, which was mostly open space and was once a golf course, did not have any specific ordinance language addressing solar panel arrays. The Board, after multiple hearings and a site visit, denied the application based on concerns raised by neighbors about the project's potential impact on the scenery, property values, and previous negative experiences with other solar projects in the city.The Board's decision was upheld by the Superior Court, which agreed with the Board's first and third reasons for denial, namely that the installation of new utility poles would create an industrial look out of place in the neighborhood, and that cutting down mature trees contradicted the purpose provisions. However, the Superior Court did not uphold the Board's second basis, that the solar panel array endangered or adversely impacted the residents, due to lack of supporting facts.The Supreme Court of New Hampshire reversed the lower court's decision, ruling that the Board could not rely solely on the purpose provisions to deny the application. The court found that the purpose provisions lacked sufficient specificity for site plan review and left the proposed project to be judged by the subjective views of the Board through ad hoc decision making. The court granted the plaintiffs a builder's remedy, allowing them to proceed with their development provided they comply with all other applicable regulations. View "Mojalaki Holdings v. City of Franklin" on Justia Law
H&T Fair Hills, Ltd. v. Alliance Pipeline L.P.
Alliance Pipeline L.P. (“Alliance”) entered into contracts with four states (“State Agreements”) as well as contracts with individual landowners in order to build a natural gas pipeline. The contracts with landowners provide easements for the pipeline right-of-way. In 2018, some landowners on the pipeline right-of-way filed a class-action lawsuit against Alliance. After the class was certified, Alliance moved to compel arbitration for the approximately 73 percent of plaintiffs whose easements contain arbitration provisions. Alliance appealed, arguing the district court erred by not sending all issues to arbitration for the plaintiffs whose easements contain arbitration provisions.
The Eighth Circuit affirmed in part and reversed in part. The court explained that the district court that the damages issues are subject to arbitration for the plaintiffs whose easements contain an arbitration provision. Plaintiffs make two arguments against sending any issues to arbitration: (1) Plaintiffs’ claims cannot be within the scope of the arbitration provisions because the claims allege lack of compensation for “ongoing yield losses,” not “damages to crops” and (2) Plaintiffs’ claims arise under the State Agreements, which do not have arbitration provisions. The court found the arbitration agreements to be enforceable and to cover all issues. The court held that as to the arbitration class members, the claims should be dismissed without prejudice. As to the members of the class without arbitration provisions, the court saw no reason why these class members cannot proceed with the lawsuit in the normal course at the district court. View "H&T Fair Hills, Ltd. v. Alliance Pipeline L.P." on Justia Law
Western Watersheds Project, et al. v. United States Bureau of Land Management, et al.
Three conservation groups challenged the U.S. Bureau of Land Management’s approval of Jonah Energy’s development project on state and federal land in Wyoming. The project was designed to drill exploratory wells on land for which Jonah possessed development rights. The conservation groups argued the district court erred in upholding the BLM’s approval under the National Environmental Protection Act and the Federal Land Polocy and Management Act. Specifically, they contended the BLM inadequately considered the impact of the project on the sage-grouse and pronghorn antelope migration and grazing patterns. The Tenth Circuit concluded the BLM adequately collected and considered information on the sage-grouse and pronghorn, and selected a development plan that met statutory requirements. View "Western Watersheds Project, et al. v. United States Bureau of Land Management, et al." on Justia Law
Green Development, LLC v. Town of Exeter
The Supreme Court affirmed the judgment of the superior court in favor of the Town of Exeter in this action seeking injunctive and declaratory relief challenging the Town's decision to amend its zoning ordinance, which prevented Plaintiff from developing three commercial solar-field projects in Exeter, holding that Plaintiff was not entitled to relief on its allegations of error.On appeal, Plaintiff challenged several aspects of the superior court's judgment denying Plaintiff's request to enjoin enforcement of an emergency moratorium ordinance preventing review of Plaintiff's solar-field projects and to declare that Plaintiff's solar-field projects were vested pursuant to R.I. Gen. Laws 45-24-44. The Supreme Court affirmed, holding that, under this Court's understanding of the relevant law, the trial court properly entered judgment in favor of the Town. View "Green Development, LLC v. Town of Exeter" on Justia Law
Driftless Area Land Conservancy v. Rural Utilities Service
Utility companies responsible for a planned electric transmission line asked the Fish and Wildlife Service (FWS) to allow construction across the Upper Mississippi River National Wildlife and Fish Refuge alongside an existing road and railroad. Rural Utilities Service completed an environmental impact statement under the National Environmental Policy Act (NEPA), 42 U.S.C. 4332(2)(C). FWS adopted the statement and issued a right-of-way permit.While litigation was pending, the utility companies sought to slightly alter the route and asked FWS to consider a land exchange. FWS discovered that it had relied on incorrect easement documents in issuing its original determination. It revoked the determination and permit but promised to consider the proposed land exchange. The district court ruled in favor of the environmental groups but declined to enjoin ongoing construction of the project on private land outside the Refuge.The Seventh Circuit vacated in part, first rejecting a mootness argument. FWS has revoked the compatibility determination but has not promised never to issue a new permit. However, FWS’s current position does not meet the criteria of finality. Whatever hardship the plaintiffs face comes not from FWS’s promise to consider a land exchange but from the Utilities’ decision to build on their own land, so the district court erred in reviewing the merits of the proposed land exchange. Plaintiffs’ request for relief against the Utilities under NEPA likewise is premature. Adopting the environmental impact statement did not “consummate” the decisionmaking process. View "Driftless Area Land Conservancy v. Rural Utilities Service" on Justia Law
City of Hesperia v. Lake Arrowhead Community Services Dist.
This appeal was the second relating to a suit brought by the City of Hesperia (the City) against respondents Lake Arrowhead Community Services District and the Board of Directors of Lake Arrowhead Community Services District (jointly, the District) regarding a proposed 0.96-megawatt solar photovoltaic project (the Solar Project) that the District had been planning to develop on six acres of a 350-acre property it owned, known as the Hesperia Farms Property. The Hesperia Farms Property was located within the City’s municipal boundary and was generally subject to the City’s zoning regulations. The District first approved its Solar Project in December 2015, after determining that the project was either absolutely exempt from the City’s zoning regulations under Government Code section 53091, or qualifiedly exempt under Government Code section 53096. The City sought a writ of mandate prohibiting the District from further pursuing the Solar Project. In Hesperia I, the Court of Appeal determined the District’s Solar Project was not exempt from the City’s zoning regulations under Government Code section 53091’s absolute exemption, or under Government Code section 53096’s qualified exemption. The Court concluded, however, that Government Code section 52096’s qualified exemption did not apply to the District’s approval of the Solar Project only because the District had failed to provide substantial evidence to support its conclusion that there was no other feasible alternative to its proposed location for the Solar Project. This result left open the possibility that the District could undertake further analyses and show that there was no feasible alternative to the Solar Project’s proposed location in order to avoid application of the City’s zoning ordinances. A few months after the District made its second no-feasible-alternative determination with respect to the Solar Project, the City filed a second petition for writ of mandate and complaint challenging the Solar Project. The trial court ultimately denied the City’s second petition. When the City appealed, the Court of Appeal concluded the trial court did not err in rejecting the City’s petition for writ of mandate. View "City of Hesperia v. Lake Arrowhead Community Services Dist." on Justia Law
Aanonsen v. Bd. of County Commissioners of Albany County
The Supreme Court affirmed the judgment of the district court affirming the decision of the Board of County Commissioners of Albany County approving ConnectGen Albany County LLC's application for a Wind Energy Conversion System (WECS) permit to construct a wind farm on Albany County land, holding that Appellants were not entitled to relief.Specifically, the Supreme Court held (1) contrary to Appellants' argument on appeal, ConnectGen was not required to obtain a conditional use permit in addition to the WECS special use permit; (2) the Board's approval of the WECS special use permit was not arbitrary or capricious; and (3) Appellants failed to establish that the Board's approval of the WECS special use permit was a taking of private property in violation of Wyo. Const. art. 1, 32. View "Aanonsen v. Bd. of County Commissioners of Albany County" on Justia Law
AVCG, LLC v. Alaska Department of Natural Resources
Alaska Venture Capital Group, LLC (AVCG) owned interests in oil and gas leases on state lands. AVCG sought the State’s approval to create overriding royalty interests on the leases. The Alaska Department of Natural Resources, Division of Oil and Gas denied AVCG’s requests, explaining that the proposed royalty burdens jeopardized the State’s interest in sustained oil and gas development. AVCG appealed. Five years later the DNR Commissioner affirmed. The superior court then affirmed the Commissioner’s decisions. AVCG appealed to the Alaska Supreme Court, arguing primarily that the decisions improperly adopted a new regulation that did not undergo the rulemaking procedures of Alaska’s Administrative Procedure Act (APA). AVCG maintained that DNR’s reliance on specific factors - in particular, the fact that the proposed ORRIs would create a total royalty burden of over 20% on the leases - amounted to adopting a regulation. AVCG also argued that the decisions lacked a reasonable basis in fact and law and that, for some of its leases, no agency approval was required at all. The Supreme Court rejected these arguments, and rejected AVCG's constitutional claim: that delay and an "ad hoc" decision-making process violated its procedural due process rights. View "AVCG, LLC v. Alaska Department of Natural Resources" on Justia Law
Stop B2H Coalition v. Dept. of Energy
Petitioners sought the Oregon Supreme Court's review of an order of the Energy Facility Siting Council (EFSC) that approved an Idaho Power Company (Idaho Power) application for a site certificate to construct a high-voltage electrical transmission line from Boardman, Oregon, to Hemingway, Idaho. Petitioner STOP B2H Coalition (Stop B2H) contended that EFSC erred by : (1) denying Stop B2H’s request for full party status in the contested case proceedings; (2) granting an exception or variance to noise level requirements; (3) modifying the governing rule to limit the noise assessment to landowners within one-half mile of the transmission line; and (4) misapplying EFSC’s rules on the visual impacts from the transmission line. Petitioner Michael McAllister contended EFSC erred by failing to require Idaho Power to include in its application an “environmentally preferable” location for a segment of the transmission line in Union County. Petitioner Irene Gilbert contended EFSC erred by: (1) denying Gilbert’s request for full party status; (2) failing to document the impacts on historic properties and mitigation measures; (3) delegating future approval of mitigation plans to the Oregon Department of Energy (ODOE); (4) relying on federal standards to determine mitigation requirements for historic properties; and (5) modifying a mandatory site certificate condition without rulemaking. Applying the governing standard of review, the Supreme Court affirmed EFSC’s final order approving the site certificate for this transmission line. View "Stop B2H Coalition v. Dept. of Energy" on Justia Law