In the case of Planning and Conservation League et al., v. Department of Water Resources heard in the California Court of Appeal, Third Appellate District, the court considered whether the Department of Water Resources’ (department) approval of amendments to long-term contracts with local government agencies that receive water through the State Water Project violated various laws. The amendments extended the contracts to 2085 and expanded the facilities listed as eligible for revenue bond financing. Several conservation groups and public agencies challenged the amendments, arguing they violated the California Environmental Quality Act (CEQA), the Sacramento-San Joaquin Delta Reform Act (Delta Reform Act), and the public trust doctrine. However, the court held that the department did not violate CEQA, the Delta Reform Act, or the public trust doctrine, and therefore affirmed the trial court's judgment in favor of the department. The court found that the department used the correct baseline for its environmental impact report (EIR), properly segmented the amendments from related projects, and adequately considered the direct, indirect, and cumulative impacts of the amendments. The court also held that the department adequately described the project and considered a reasonable range of alternatives, and that recirculation of the EIR was not required. The court rejected arguments that the amendments violated the Delta Reform Act or the public trust doctrine, finding that they did not impact "water that is imbued with the public trust." The court concluded that the department acted within its authority in approving and executing the amendments. View "Planning and Conservation League v. Dept. of Water Resources" on Justia Law

by
In the case before the Supreme Court of the State of South Dakota, Love’s Travel Stops & Country Stores and One Shot, LLC, filed a petition against the City of Wall, South Dakota, City Council, and Planning and Zoning Commission for the City. Love’s, a corporation that operates 24-hour truck stops, entered into an agreement to purchase a 13-acre parcel of land from One Shot, contingent on obtaining the necessary zoning and permitting approvals from the city. After the City Council denied Love's rezoning and building permit applications, Love’s filed a petition for writ of mandamus, writ of certiorari, and request for declaratory relief with the circuit court. The circuit court granted Love's petition in part, declaring that the City’s Zoning Ordinance did not apply to the property and required the City to reconsider Love's application for a building permit. The City Council reconsidered and again denied Love's building permit application. Love’s then filed a motion for order to show cause requesting the circuit court to find the City in contempt of the court’s order and sought issuance of a building permit. The circuit court found the City in contempt and ordered the City to issue Love's a building permit. The City appealed.The South Dakota Supreme Court reversed the circuit court's decision. The Supreme Court found that the circuit court order was clearly erroneous in finding that the City willfully and contumaciously violated the court’s order to reconsider and vote on Love's requested building permit. The Supreme Court also noted that the circuit court’s remedy for its finding of contempt was inconsistent with the purpose of civil contempt and exceeded its authority by imposing a punitive, rather than coercive civil contempt remedy. The court's order to issue a building permit was punitive and denied the City the opportunity to purge itself of contempt and come into compliance with the original court order. Therefore, the Supreme Court reversed the circuit court’s finding of contempt and the order issuing a building permit to Love's. View "Love’s Travel Stops V. City Of Wall" on Justia Law

by
In the case before the United States Court of Appeals for the Second Circuit, Ateres Bais Yaakov Academy of Rockland (ABY) sued the Town of Clarkstown, George Hoehmann, CUPON Inc., and Citizens United to Protect Our Neighborhoods of Greater Nanuet Inc. ABY, a religious educational institution, planned to purchase property in Clarkstown, New York, to establish an Orthodox Jewish school. It alleged that the Defendants manipulated an ostensibly neutral building permit application and zoning appeals process to block this construction. The district court dismissed the complaint for lack of subject matter jurisdiction, concluding that ABY's religious discrimination and civil rights claims were not ripe as it had not received a final decision from the town’s Zoning Board of Appeals (ZBA) and that the lost-contract injury underpinning ABY’s tortious interference claim was not traceable to the Town Defendants.In this appeal, the Second Circuit disagreed with the district court. The Second Circuit found that the ZBA's refusal to adjudicate ABY's appeal of its permit application constituted a final decision for ripeness purposes. The court also determined that ABY had plausibly alleged a causal connection between the Town Defendants’ actions and the injuries resulting from ABY's lost contract with Grace Church. Therefore, the Second Circuit reversed the district court's judgment and remanded the case for further proceedings. View "Ateres Bais Yaakov Academy of Rockland v. Town of Clarkstoawn" on Justia Law

by
The Supreme Court of Alabama reversed a lower court's judgment regarding the denial of a preliminary plat for a proposed development within the geographical limits of the City of Montgomery. The plaintiffs, T Investments, LLC, and FHM Company, LLLP, contested the Montgomery Circuit Court's judgment that refused their petition for a writ of mandamus directing the City of Montgomery Planning Commission to conditionally approve their preliminary plat. The Supreme Court found that the City of Montgomery Planning Commission's decision to deny approval on the basis of "safety reasons" was insufficiently specific and did not comply with the requirement that valid and sufficiently clear grounds for the denial of a subdivision plat be recorded. The court held that the failure to meet this requirement resulted in the automatic approval of the preliminary plat and ordered the lower court to grant the petition for the writ of mandamus. View "T Investments, LLC v. City of Montgomery Planning Commission" on Justia Law

by
In 1882-1883, the Railway acquired property and constructed the now-abandoned railroad line. In 2008, the Railway filed a notice of exemption from formal abandonment proceedings with the Surface Transportation Board (STB). The Illinois Department of Natural Resources showed interest in railbanking and interim trail use under the 1983 National Trails System Act Amendments, 16 U.S.C. 1247(d). The STB issued a Notice of Interim Trail Use (NITU). The owners of property adjoining the railroad line sued, alleging takings by operation of the Trails Act with respect to 51 parcels; 22 parcels were conveyed by instruments including the words “right of way” (ROW Agreements); three were conveyed by instruments including the words “for railroad purposes” (Purpose Agreements); and three are those for which no instruments were produced.The Claims Court granted the government summary judgment, finding that the Railway held the ROW Agreement and Purpose Agreement parcels in fee simple and that the owners failed to show that they had cognizable property interests in the non-instrument parcels. The Federal Circuit reversed. The court rejected the government’s argument that using the term “right of way” in the ROW Agreements referred to the land conveyed, not a limitation on the interest conveyed. For the Purpose Agreements, the Claims Court mistakenly relied on cases discussing deeds that did not include an expression of purpose in the granting clause. Illinois law indicates that the Railway obtained, at most, an easement over the non-instrument parcels. View "Barlow v. United States" on Justia Law

by
Plaintiffs are Constance Swanston (“Swanston”), Shannon Jones (“Jones”), and Women’s Elevated Sober Living, LLC (“WESL”) (collectively, “Plaintiffs”). Swanston is an individual in recovery from substance use disorders (“SUDs”) and the owner and operator of WESL. In November 2018, WESL opened a sober living home (the “Home”) on Stoney Point Drive in Plano, Texas. Jones is a caretaker and resident of the Home. Defendant-Appellant, the City of Plano (the “City”) appealed the district court’s judgment holding that it violated the Fair Housing Act (“FHA”) due to its failure to accommodate Plaintiffs as to the capacity limits in the applicable zoning ordinance. The district court enjoined the City from (1) restricting the Home’s occupancy to fewer than fifteen residents; (2) enforcing any other property restriction violative of the FHA or ADA; and (3) retaliating against Plaintiffs for pursuing housing discrimination complaints under the FHA and ADA. Following a hearing, awarded Plaintiffs nominal damages of one dollar.   The Fifth Circuit vacated the district court’s injunction and remanded it. The court held that the district court erred in determining that the evidence satisfied the applicable legal standard. The court explained that the Third Circuit concluded that, based on its strict reading of Section 3604(f)(3)(B) and the prior jurisprudence in its court and its sister circuits, the resident failed to prove that her requested accommodation was necessary considering the definition of the term, the purpose of the FHA, and the proffered alternatives. The court wrote that for the same reasons, it holds that Plaintiffs have failed to establish that their requested accommodation was therapeutically necessary. View "Women's Elevated v. City of Plano" on Justia Law

by
In consolidated appeals, the City of Orange Beach ("the City") appealed a judgment entered in favor of Ian Boles in regard to a dispute over the City's inspection of Boles' property. Between 2013 and 2015 Boles constructed two eight-bedroom duplexes on property he owned located within the City limits ("the beachfront property"). In September 2015, Boles filed a building-permit application seeking a permit to construct two additional multiple-level duplexes on the beachfront property. Additionally, in October 2015, Boles filed a separate building-permit application for the construction of a single-family dwelling on another parcel of property that Boles owned within the City limits ("the Burkhart Drive property"). At the time of each permit request, Boles completed a "Home Builders Affidavit" attesting that he was the owner of the property; that he would be acting as his own contractor on the proposed project, which would not be offered for sale; and that he was, thus, exempt from the requirement that he be licensed under Alabama's Home Builders Licensure Law. The building-permit packages provided to Boles explained that a certificate of occupancy for the proposed structure would not be issued until, among other things, "a subcontractor list has been submitted to the [City's] Finance Department." Boles also received with each package a blank subcontractor form for identifying all subcontractors for the proposed project, which specified that it was due within 10 days of the issuance of the building permits. Boles proceeded with construction on the two properties without completing or returning the subcontractor form for either property. Boles's electrical subcontractor apparently contacted the City to request an electrical meter-release inspection upon completion of the electrical portion of that project; the City refused. Boles contended the City either lacked the authority to and/or were exceeding their authority in refusing to inspect the beachfront property until the City received information to which, according to Boles, it was not entitled. The Alabama Supreme Court concluded the trial court erred both in submitting Boles's damages claims to a jury and in denying the City's motion seeking a judgment as a matter of law. The trial court's judgment was reversed, and these matters were remanded for further proceedings. View "City of Orange Beach v. Boles." on Justia Law

by
Snowball West Investments, LP applied to build a housing project consisting of 215 homes in the Sunland/Tujunga area of the City of Los Angeles. The current zoning for the site is RA and A1; the project must be rezoned to RD5 and R1 for the project to move forward. The City denied Snowball’s zone change request, stating that more information was needed before building homes in a high wildfire hazard area. Snowball petitioned for a writ of mandate, which was denied. Snowball appealed. Snowball argues that under the rezoning exemption in the Housing Accountability Act (HAA), Government Code section 65589.5, subdivision (j)(4)1 (section 65589.5(j)(4)), its project is exempt from the need for a zone change.   The Second Appellate District affirmed the superior court’s denial of Snowball’s writ petition. The court explained that the current RA and A1 zoning is consistent with the community plan through the language of that plan. Because the rezoning exemption in section 65589.5(j)(4) only applies when “the zoning for the project site is inconsistent” with the applicable plan, the rezoning exemption in section 65589.5(j)(4) does not apply here, and Snowball’s project was not exempt from zone change requirements.  Further, the court wrote that the HAA does not apply, and the City’s findings were sufficient under the LAMC and supported by substantial evidence. View "Snowball West Investments v. City of Los Angeles" on Justia Law

by
The Court of Appeals reversed the decision of the appellate division affirming the judgment of Supreme Court granting Respondents' motions to dismiss Petitioners' amended N.Y. C.P.L.R. 78 petition as time-barred, holding that the relation back doctrine applied.In 2012, Petitioners secured an injunction barring Respondents from using part of their property for nonresidential purposes. Thereafter, Respondents sought a variance from the Village of Hancock Board of Appeals (ZBA), which was granted. Petitioners later commenced a CPLR article 78 proceeding seeking annulment of the use variation. The appellate division granted the request and reversed. In 2016, Respondents sought a variance, which the ZBA granted. Petitioners subsequently commenced this CPLR article 78 proceeding seeking annulment of the ZBA's decision. This time, however, Petitioners omitted Respondent Rosa Kuehn. Supreme Court granted Respondents' motion to dismiss, concluding that the petition was time-barred against Rosa and that the claims against the remaining respondents must be dismissed for lack of a necessary party. The appellate division affirmed. The Court of Appeals reversed, holding that the relation back doctrine is not limited to cases where the amending party's omission results from doubts regarding the omitted party's identity or status. View "Nemeth v. K-Tooling" on Justia Law

by
Petitioners James Beal, Mary Beth Brady, Mark Brighton, Lenore Weiss Bronson, Nancy Brown, William R. Castle, Lawrence J. Cataldo, Ramona Charland, Lucinda Clarke, Fintan Connell, Marjorie P. Crean, Ilara Donarum, Joseph R. Famularo, Jr., Philippe Favet, Charlotte Gindele, Julia Gindele, Linda Griebsch, Catherine L. Harris, Roy W. Helsel, John E. Howard, Nancy B. Howard, Elizabeth Jefferson, Cate Jones, Robert McElwain, Mary Lou McElwain, Edward Rice, April Weeks, Michael Wierbonics, and Lili Wierbonics, appealed a Housing Appeals Board (HAB) order that reversed a decision of the Portsmouth Zoning Board of Adjustment (ZBA), which, in turn, had reversed certain approvals granted by the Portsmouth Planning Board (Planning Board) to respondent, Iron Horse Properties, LLC (Iron Horse). Iron Horse owned real property at 105 Bartlett Street in Portsmouth. In 2021, it requested various approvals from the Planning Board in connection with its proposed redevelopment of the site: three multi-family apartment buildings with a total of 152 dwelling units. Iron Horse sought a site review permit, lot line revision permit, conditional use permit (CUP) for shared parking, and a wetland CUP. The Planning Board granted the approvals, and the petitioners, describing themselves as “a group of abutters and other concerned citizens,” then filed an appeal with the ZBA. The ZBA granted the appeal, effectively reversing the Planning Board’s site plan and CUP approvals. Following denial of its motion for rehearing, Iron Horse then appealed the ZBA’s decision to the HAB. The HAB reversed the ZBA’s findings as to six of the petitioners’ claims and dismissed the remaining three claims. Petitioners took their appeal to the New Hampshire Supreme Court, raising a number of issues that were consolidated under two overarching questions: (1) whether Iron Horse’s proposed project met the six criteria for a wetland CUP set forth in section 10.1017.50 of the Portsmouth Zoning Ordinance; and (2) whether Iron Horse’s permit requests were barred under the doctrine of Fisher v. City of Dover, 120 N.H. 187 (1980). Finding no reversible error in the HAB’s decision, the Supreme Court affirmed. View "Appeal of Beal, et al." on Justia Law