First Security v. Belle Ranch
Three cases were consolidated by the Idaho Supreme Court for the purposes of appeal. The cases involved three separate actions: one brought by First Security Corporation and two others brought by Richard Fosbury to quiet title to their purported ownership of irrigation water rights to land owned by Belle Ranch, LLC. All parties agreed that partial decrees for the water rights were issued in the Snake River Basin Adjudication (SRBA) in the name of South County Estates, LLC. As South County’s successors in interest, First Security and Fosbury argued their interests in the water rights are senior and therefore superior to the interest of Belle Ranch, LLC. Notwithstanding these claims, the district court quieted title to the water rights in question to Belle Ranch, LLC. First Security and Fosbury appeal. The Idaho Supreme Court determined First Security and Fosbury’s claims were precluded by res judicata: the claims were the same claims that were adjudicated in the SRBA. The Supreme Court found it was appropriate for the district court to quiet title in favor of Belle Ranch, LLC, because Belle Ranch, LLC, filed a notice of a change in ownership during the pendency of the SRBA. Accordingly, the Court affirmed the district court’s judgment. View "First Security v. Belle Ranch" on Justia Law
Maacama Watershed Alliance v. County of Sonoma
The 86-acre Knights Valley parcel in rural Sonoma County is zoned “Land Extensive Agriculture,” which allows wineries and tasting rooms as conditional uses. The project is a two-story, 5,500-square-foot winery building with a 17,500-square-foot wine cave, wastewater treatment, water storage facilities, fire protection facilities, and mechanical areas, covering approximately 2.4 acres. The site contains two residences and 46 acres of vineyards. The nearby area is primarily vineyards. County staff reviewed reports considering impacts on geology, groundwater, wastewater, and biological resources, and concluded that, with recommended mitigation, the project would not have a significant effect on the environment. The county approved the use permit with conditions and adopted a mitigated negative declaration under the California Environmental Quality Act (Pub. Resources Code 21000) and a mitigation monitoring program. The court of appeal upheld the approval. Opponents did not provide evidence that the project is reasonably likely to cause landslides or otherwise generate environmentally harmful releases of debris; that erosion from the project, particularly runoff from the cave spoils, will cause significant effects on Bidwell Creek and degrade the habitat for salmonids; or that the project’s groundwater use will significantly affect salmonids, groundwater supply in neighboring wells, and fire suppression. There was no substantial evidence that the winery will have a significant aesthetic impact or that there is a reasonable possibility the project, as conditioned, will significantly increase the risk of wildfires. View "Maacama Watershed Alliance v. County of Sonoma" on Justia Law
Watkins Development, LLC v. Jackson Redevelopment Authority
The Jackson Redevelopment Authority (JRA) leased several parcels along Farish Street in Jackson, Mississippi to the Farish Street Group (FSG). In exchange for a long-term lease and other favorable terms, FSG was given a set period of time to renovate the properties and to sublet them to retail establishments. Watkins Development, which owned half of FSG, contracted with FSG to do the renovations. The plan was to build an entertainment district on Farish Street, but after a few years only a fraction of the renovations were done, and none of the properties were occupied by tenants. JRA terminated the lease, and this litigation followed. The Chancery Court ultimately found that the lease was properly terminated, that no party had shown it was entitled to money damages, and that Watkins Development could not take a mechanic’s lien on the property. Finding no reversible error in that judgment, the Mississippi Supreme Court affirmed. View "Watkins Development, LLC v. Jackson Redevelopment Authority" on Justia Law
United States v. Idaho
Four appeals arose from a consolidated subcase that was a part of the broader Coeur d’Alene-Spokane River Basin Adjudication (CSRBA). The United States Department of the Interior (the United States), as trustee for the Coeur d’Alene Tribe (the Tribe), filed 353 claims in Idaho state court seeking judicial recognition of federal reserved water rights to fulfill the purposes of the Coeur d’Alene Tribe’s Reservation (the Reservation). The Tribe joined the litigation. The State of Idaho (the State) and others objected to claims asserted by the United States and the Tribe. The district court bifurcated the proceedings to decide only the entitlement to water at this stage, with the quantification stage to follow. After cross-motions for summary judgment, the district court allowed certain claims to proceed and disallowed others. The district court specifically allowed reserved water rights for agriculture, fishing and hunting, and domestic purposes. The district court allowed reserved water rights for instream flows within the Reservation, but disallowed those for instream flows outside the Reservation. The district court determined priority dates for the various claims it found should proceed to quantification, holding generally the Tribe was entitled to a date-of-reservation priority date for the claims for consumptive uses, and a time immemorial priority date for nonconsumptive uses. However, in regard to lands homesteaded on the Reservation by non-Indians that had since been reacquired by the Tribe, the district court ruled the Tribe was entitled to a priority date of a perfected state water right, or if none had been perfected or it had been lost due to nonuse, the Tribe’s priority date would be the date-of-reacquisition. The Idaho Supreme Court affirmed in part and reversed in part. The Supreme Court determined the district court improperly applied the controlling case law's rule of "primary-secondary" distinction and instead should have allowed aboriginal purposes of plant gathering and cultural uses under the homeland purpose theory. Furthermore, the Court determined the priority date associated with nonconsumptive water rights was time immemorial. The Court affirmed the remainder of the district court’s decisions and remanded for further proceedings. View "United States v. Idaho" on Justia Law
In re Diverging Diamond Interchange SW Permit, Diverging Diamond Interchange A250
Plaintiffs R.L. Vallee, Inc. (Vallee) and Timberlake Associates, LLP (Timberlake) appealed various aspects of three decisions that culminated in the environmental division granting the Vermont Agency of Transportation (VTrans) Act 250 and stormwater discharge permits for a highway project involving the reconfiguration of an interstate exit. The Vermont Supreme Court concluded the environmental division erred in dismissing Vallee’s questions regarding Criterion 1 of Act 250; in all other respects, the Court affirmed. Accordingly,issuance of the stormwater permit was upheld, issuance of the Act 250 permit was reversed, and the matter remanded for the environmental division to consider Vallee’s questions concerning Criterion 1. View "In re Diverging Diamond Interchange SW Permit, Diverging Diamond Interchange A250" on Justia Law
Girard v. Town of Plymouth
Plaintiffs Denis Girard and Florence Leduc appealed a superior court order upholding a decision of the Town of Plymouth Planning Board denying their subdivision application. They argued the trial court erred in upholding the planning board’s denial of their application because: (1) the board “engaged in impermissible ad hoc rule” and “decision making” when it relied upon an “overly broad” subdivision regulation; (2) the board relied on a subdivision regulation that did not specifically authorize the board to regulate wetlands; (3) the board’s regulation of wetlands is preempted by State statute; (4) the trial court unreasonably relied on certain evidence provided by a wetlands scientist; (5) the board’s decision to reject the application based upon the proposed subdivision’s impact on the wetlands was unreasonable; and (6) the board violated New Hampshire law by discussing the application at a hearing without notice to the applicants or the public. Finding no reversible error, the New Hampshire Supreme Court affirmed. View "Girard v. Town of Plymouth" on Justia Law
McInturff v . Shippy
This appeal stemmed from a disputed water right relating to the St. Joe River in Benewah County, Idaho, between a landowner and the tenants who put the water to beneficial use. The license at issue described the water right as “appurtenant to the described place of use.” The landowner argued the water right was appurtenant to his land, while the tenants contended the right was developed and owned by their predecessors in interest and now belonged to them by virtue of their having purchased the interest. The district court ultimately adopted the Special Master’s report and issued a partial decree, which listed the tenants as the owner of the license. Finding no reversible error in that decision, the Idaho Supreme Court affirmed. View "McInturff v . Shippy" on Justia Law
Eagle Creek Irrigation v. A.C & C.E Investments
Eagle Creek Irrigation Company (“Eagle Creek”) appealed a district court's grant of summary judgment in favor of A.C. & C.E. Investments, Inc. The dispute centered on 15 shares of Eagle Creek stock which authorized the holder to divert 30 cfs of water (or 15 miner’s inches) of Eagle Creek’s water right. AC&CE Investments purchased 15 acres (“the Property”) located within Eagle Creek’s boundaries. The prior property owners also owned 15 shares in Eagle Creek stock. The question presented on appeal was whether the 15 shares passed as an appurtenance to the Property. The district court ruled that AC&CE Investments acquired 15 shares in Eagle Creek when it acquired title to the Property because the shares passed as an appurtenance to the Property. Eagle Creek appealed. The Idaho Supreme Court determined the district court erred in granting summary judgment to AC&CE Investments because the district court did not look to Eagle Creek’s governing documents. The Supreme Court therefore vacated the portion of the district court’s final judgment which stated that the 15 shares of the Eagle Creek stock were appurtenant to the Property. View "Eagle Creek Irrigation v. A.C & C.E Investments" on Justia Law
In re North East Materials Group, LLC/Rock of Ages Corp. Act 250 Permit
Appellants, Neighbors for Healthy Communities (Neighbors), appealed the Environmental Division’s decision to grant an Act 250 permit application to appellees, North East Materials Group, LLC (NEMG) and Rock of Ages Corp. (ROA), for a rock-crushing operation in Graniteville in the Town of Barre. Neighbors argued the court erred in granting NEMG’s application because the proposed operation does not comply with either Act 250 Criterion 1, with respect to air pollution due to silica dust, or Criterion 8, with respect to noise from off-site truck traffic. The Vermont Supreme Court found the trial court committed no error in concluding that NEMG’s rock-crushing operation complied with Act 250 Criterion 1 and Criterion 8. View "In re North East Materials Group, LLC/Rock of Ages Corp. Act 250 Permit" on Justia Law
Valbruna Slater Steel Corp. v. Joslyn Manufacturing Co.
Valbruna purchased the steel mill at a 2004 bankruptcy auction and began cleanup efforts under the Resource Conservation and Recovery Act, 42 U.S.C. 6901. In 2000, Slater, the site’s then-owner, had unsuccessfully sued Joslyn, which had owned and operated the site from 1928-1981, in state court seeking indemnification under the parties’ contract and costs under Indiana’s Environmental Legal Actions (ELA) statute. In 2010, Valbruna sued Joslyn under the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA), 42 U.S.C. 9613(b), and ELA. Joslyn’s fault is undisputed. Joslyn raised claim-preclusion, statute-of-limitations, and contribution defenses. The district court found that the CERCLA claim was not precluded, but the ELA claim was, and that the suit was timely. The court imposed equitable contribution on Valbruna, requiring it to pay for 25% of past and future cleanup costs. The Seventh Circuit affirmed, agreeing that the CERCLA claim was not precluded. If there is no state-court jurisdiction to hear an exclusively federal claim, there is no claim preclusion. The claim was not barred as being filed more than six years after the start of “remedial action.” Slater’s earlier cleanup was “removal.” While the 25% imposition on a no-fault owner "reached the limits" of the court's discretion, there was no abuse of that discretion. Valbruna understood the site’s pollution problems before purchasing it and apparently paid far less than the asking price; the court was rationally concerned about a windfall for Valbruna. View "Valbruna Slater Steel Corp. v. Joslyn Manufacturing Co." on Justia Law