Lincoln Land Development, LLP v. City of Lincoln

by
The City of Lincoln appealed a district court’s amended judgment awarding damages and attorney fees for taking land owned by Lincoln Land Development, LLP. In the mid-1980s the City of Lincoln established a narrow, two-tire-track dirt road over private property to access its wastewater treatment site. In 2005 Lincoln Land Development purchased the property. In 2011 the City improved the dirt road by raising the road profile, widening the road top, constructing ditches, installing culverts and completing gravel resurfacing to standardize the width and height of the road. The City did not obtain permission from Lincoln Land Development before commencing the improvement project and did not initiate eminent domain proceedings. Lincoln Land Development sued the City in February 2015 for inverse condemnation, trespass and nuisance relating to the City’s 2011 improvement of the road. Lincoln Land Development moved to amend its complaint to assert claims relating to increased surface water drainage and damages caused by stormwater retention. The City denied a taking occurred and raised affirmative defenses, including claiming a public easement through prescriptive use, the existence of an express or implied easement, an easement by estoppel, or a government mandate required the project. The district court found Lincoln Land Development’s claims of nuisance and trespass were time-barred and dismissed them with prejudice in March 2015. In September 2017 a bench trial was held and claims based on increased surface water drainage, wetlands and stormwater retention ponds were dismissed. At the conclusion of the bench trial, the district court found that the City established a prescriptive easement in the pre-2011 road and that a taking occurred when additional property was used in the 2011 road improvement. A jury subsequently determined the value of the taking was $8,924.00 plus interest. The district court subsequently granted Lincoln Land Development’s motion for attorney fees of $122,705.50. The North Dakota Supreme Court found the district court did not err in determining that the pre-2011 two-tire-track road was under the protection of a prescriptive easement and that a taking occurred with the 2011 road improvement project. Lincoln Land Development was entitled to costs and fees. The Court therefore affirmed the amended judgment, the taking decision, and award of attorney fees. The matter was remanded for consideration of whether Lincoln Land Development should recover attorney fees on appeal. View "Lincoln Land Development, LLP v. City of Lincoln" on Justia Law