In 2006, the City of San Diego (City) obtained a Site Development Permit (SDP) to construct a new lifeguard station on Mission Beach. The SDP stated that failure to utilize the permit within 36 months of its issuance would automatically void the permit. Over the ensuing years, the City worked to secure a permit from the California Coastal Commission (Commission) and to obtain funding for the project. Largely because of the economic downtown, the City struggled to find financing for the project and no construction occurred until 2015. At that time, the City notified nearby residents that its contractor would begin construction in March. The City issued building permits in April and its contractor began initial work on the project, then stopped before the summer moratorium on beach construction. In August 2015, before the end of the moratorium, Citizens for Beach Rights (Citizens) brought a petition for writ of mandate and claim for declaratory relief seeking to halt construction on the grounds that the SDP issued in 2006 had expired. The trial court agreed with Citizens and issued a permanent injunction, preventing further construction without a new SDP. The City appealed, arguing Citizens' claims were barred by the applicable statutes of limitations or the doctrine of laches and, even if the action was not time barred, the SDP remained valid in 2015 under the City's municipal code and policies. The City also argued Citizens improperly sought declaratory relief. After review, the Court of Appeal held Citizens' action was barred by the applicable statutes of limitations and, even if Citizens' claims had been timely pursued, the SDP remained valid when construction began. View "Citizens for Beach Rights v. City of San Diego" on Justia Law